NAVEEN ADISESHA - timeline for construction of an independent house                                            
                                           
Work split                                Timeline
Pooja Paya/
foundation pooja
                        Paya/foundation pooja                     House Warming
Gruha Pravesha
  Move In
Borewell   Borewell                                                  
Structural drawing     Footing/column drawings Plinth beam drawings   roof/beam drawings   F,G,H repeat for every floor   lintel/chejja drawings   J,K,L repeat for every floor Sump drawings                            
Mud Excavation     Footing[ upto 6 feet depth depending on soil test]                                                
Steel Barbending     Footing Mat+column Plinth beam columns upto
roof bottom
roof and roof beam  5 days silence \   lintel/chejja beams     Sump/Mat+Mesh                            
Concrete     Footing Mat+column Plinth[Manual/RCC] columns upto
roof bottom
RCC preferred  5 days silence     manual conrete
for chejja and lintel
    Sump[Rich cement +
water proofing like dr Fixit ]
                           
Vibrator for concrete     mandatory mandatory mandatory mandatory
[preferred 2 vibrators,
one as backup]
5 days silence           Sump                            
Curing     1 week 1 week min columns upto
roof bottom
10 days minimum
standing water on roof
only curing           Sump                            
Centering or column boxes     columns plinth beam supports columns upto
roof bottom
roof and roof beam supports
+ Mat for roof bottom to create roughness
5 days silence     centering work for
lintel and chejja
    Sump                            
Mud Filling     Fill upto ground level + water and dimmis[to push the mud and compress it] fill up after removing
 centering [ water + dimiis]
                Sump                            
Solid Blocks/Bricks                 Wall Construction
upto Lintel
  wall construction
upto roof bottom
          Compund wall with
 few small columns to strengthen the wall
                   
Electrical   Bescom
temporary connection
Renew temporary connection
every month without fail
    Place the roof
junction boxes[Fan+light
+conduit pipes]
              Wall electrical
connection grooves using angle grinder. With Metal Switch boxes
        Electrical wiring+meter+grounding         lights/fans/fixtures      
Plumbing+sanitary   Borewell motor
+hose pipe 
                      Bathroom and kitchen
grooves using angle grinder
Inside Sanitary outside sanitary
 till front compound
sanitary chambers External piping + test for water pressure + leaks if any Bathroom tiles
[ work comes under granite people below]
    Sanitary fittings
faucets/commode/sinks/etc
         
Gas connection                               kitchen groove
 for gas pipe
                     
Windows                                         uPVC windows
measurements after internal plasting
    uPVC windows installation      
Doors                           Main Door Vaskal [ auspicious day]             Indoor door
frames using anchor bolts 
Fix Main door frame and Indoor flush door frames
[unpolished]
         
Flooring                             ground floor Dappa jalli
conrete[Big jalli stones] once sanitary is laid.
      granite flooring
+skirting
    Parking tiles          
Plasting                                 External plasting Internal plasting   Finish plasting
around skirting/Bathroom tiles
    Painting - 3 coats putty
 + 1 coat painting
+ door wood polishing
    Painting 3 coats
Finishing works
 
Gates/Grills/Steel Fabrication                           window grill     stair case fabrication   gates+external
grills fabrication
               
Painting/Polishing                                                      
Kitchen Cabinets                                           Order kitchen cabinets   Fix kitchen cabinets
+ tiles + stove + sinks
     
Wardrobes and Interiors                                                     Wardrobes
+Interios at leisure