NAVEEN ADISESHA - timeline for construction of an independent house | ||||||||||||||||||||||||||||
Work split | Timeline | |||||||||||||||||||||||||||
Pooja | Paya/ foundation pooja |
Paya/foundatio | House
Warming Gruha Pravesha |
Move In | ||||||||||||||||||||||||
Borewell | Borewell | |||||||||||||||||||||||||||
Structural drawing | Footing/column drawings | Plinth beam drawings | roof/beam drawings | F,G,H repeat for every floor | lintel/chejja drawin | J,K,L repeat for every floor | Sump drawings | |||||||||||||||||||||
Mud Excavation | Footing[ upto 6 feet depth depending on soil test] | |||||||||||||||||||||||||||
Steel Barbending | Footing Mat+column | Plinth beam | columns upto roof bottom |
roof and roof beam | 5 days silence | \ | lintel/chejja beams | Sump/Mat+Mesh | ||||||||||||||||||||
Concrete | Footing Mat+column | Plinth[Manual/RCC] | columns upto roof bottom |
RCC preferred | 5 days silence | manual conrete for chejja and lintel |
Sump[Rich cement + water proofing like dr Fixit ] |
|||||||||||||||||||||
Vibrator for concrete | mandatory | mandatory | mandatory | mandatory [preferred 2 vibrators, one as backup] |
5 days silence | Sump | ||||||||||||||||||||||
Curing | 1 week | 1 week min | columns upto roof bottom |
10 days minimum standing water on roof |
only curing | Sump | ||||||||||||||||||||||
Centering or column boxes | columns | plinth beam supports | columns upto roof bottom |
roof and roof beam supports + Mat for roof bottom to create roughness |
5 days silence | centering work for lintel and chejja |
Sump | |||||||||||||||||||||
Mud Filling | Fill upto ground level + water and dimmis[to push the mud and compress it] | fill up after removing centering [ water + dimiis] |
Sump | |||||||||||||||||||||||||
Solid Blocks/Bricks | Wall Construction upto Lintel |
wall construction upto roof bottom |
Compund wall with few small columns to strengthen the wall |
|||||||||||||||||||||||||
Electrical | Bescom temporary connection |
Renew temporary connection every month without fail |
Place the roof junction boxes[Fan+light +conduit pipes] |
Wall electrical connection grooves using angle grinder. With Metal Switch boxes |
Electrical wiring+ | lights/fans/fixtures | ||||||||||||||||||||||
Plumbing+sanitary | Borewell motor +hose pipe |
Bathroom and kitchen grooves using angle grinder |
Inside Sanitary | outside sanitary till front compound |
sanitary chambers | External piping + test for water pressure + leaks if any | Bathroom tiles [ work comes under granite people below] |
Sanitary fittings faucets/commode/sinks/etc |
||||||||||||||||||||
Gas connection | kitchen groove for gas pipe |
|||||||||||||||||||||||||||
Windows | uPVC windows measurements after internal plasting |
uPVC windows installation | ||||||||||||||||||||||||||
Doors | Main Door Vaskal [ auspicious day] | Indoor door frames using anchor bolts |
Fix Main door frame and Indoor flush door frames [unpolished] |
|||||||||||||||||||||||||
Flooring | ground floor Dappa jalli conrete[Big jalli stones] once sanitary is laid. |
granite flooring +skirting |
Parking tiles | |||||||||||||||||||||||||
Plasting | External plasting | Internal plasting | Finish plasting around skirting/Bathroom tiles |
Painting - 3 coats putty + 1 coat painting + door wood polishing |
Painting 3 coats Finishing works |
|||||||||||||||||||||||
Gates/Grills/Steel Fabrication | window grill | stair case fabrication | gates+external grills fabrication |
|||||||||||||||||||||||||
Painting/Polishing | ||||||||||||||||||||||||||||
Kitchen Cabinets | Order kitche | Fix kitchen cabinets + tiles + stove + sinks |
||||||||||||||||||||||||||
Wardrobes and Interiors | Wardrobes +Interios at leisure |